    2323'''1st week'''
    2424
    25     * Task: Research on database communication (Notepad tutorial);
     25    * Task: Research on database communication (Notepad tutorial); '''[Executed]'''
    2626
    27     * Task: Research interface design;
     27    * Task: Research interface design; '''[Executed]'''
    2828
    2929    * ''Milestone'': Know how to deal with database connection.  ''Deadline'' on July the 29th, 2011. '''[Executed]'''
     
    3131'''2th week'''
    3232
    33     * Task: Multiversion coding;
     33    * Task: Multiversion coding; '''[Executed]'''
    3434
    3535    * ''Milestone'': Multiversion integration. ''Deadline'' on August the 5th, 2011. '''[Executed]'''
    3636
    3737'''3rd week'''
    38     * Task: Exploring rating;
     38    * Task: Exploring rating; '''[Executed]'''
    3939
    40     * Task: Exploring the comment section;
     40    * Task: Exploring the comment section; '''[Executed]'''
    4141
    4242    * ''Milestone'': Stable rating know how and clear vision on how to make the comment section. ''Deadline'' on August the 12th, 2011. '''[Executed]'''
    4343
    4444'''4th week'''
    45     * Task: Coding the comment section;
     45    * Task: Coding the comment section; '''[Executed]'''
    4646
    47     * ''Milestone'': Comment section integration. ''Deadline'' on August the 19th, 2011.
     47    * ''Milestone'': Comment section integration. ''Deadline'' on August the 19th, 2011. '''[Executed]'''
    4848
    4949'''5th week'''
    50     * Task: Reply to comment enhancement;
     50    * Task: Reply to comment enhancement; '''[In progress]'''
    5151   
    52     * ''Milestone'': Reply enhancement introduction. ''Deadline'' on August the 26th, 2011.
     52    * ''Milestone'': Reply enhancement introduction. ''Deadline'' on August the 26th, 2011. '''[In progress]'''
    5353
    5454'''6nd week'''
    5555
    56     * Task: Code analysis of Aptoide for rating;
     56    * Task: Code analysis of Aptoide for rating; '''[In progress]'''
    5757
    58     * Task: Coding rating functionality;
     58    * Task: Coding rating functionality; '''[In progress]'''
    5959
    60     * ''Milestone'': Rating integration. ''Deadline'' on August the 2nd, 2011.
     60    * ''Milestone'': Rating integration. ''Deadline'' on August the 2nd, 2011. '''[In progress]'''
     61
     62    * Alternatively if the work of this week is finished the 5th week... ''Milestone'': Merge project with version aptoide version being developed by Duarte Silveira.
    6163
    6264'''7th week'''