Changes between Version 36 and Version 37 of aptoide2011


Ignore:
Timestamp:
Sep 5, 2011, 3:10:25 PM (9 years ago)
Author:
rafael.campos
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • aptoide2011

    v36 v37  
    4848
    4949'''5th week'''
    50     * Task: Reply to comment enhancement; '''[In progress]'''
     50    * Task: Reply to comment enhancement; '''[Executed]'''
    5151   
    52     * ''Milestone'': Reply enhancement introduction. ''Deadline'' on August the 26th, 2011. '''[In progress]'''
     52    * ''Milestone'': Reply enhancement introduction. ''Deadline'' on August the 26th, 2011. '''[Executed]'''
    5353
    5454'''6nd week'''
    5555
    56     * Task: Code analysis of Aptoide for rating; '''[In progress]'''
     56    * Task: Code analysis of Aptoide for rating; '''[Executed]'''
    5757
    58     * Task: Coding rating functionality; '''[In progress]'''
     58    * Task: Coding rating functionality; '''[Executed]'''
    5959
    60     * ''Milestone'': Rating integration. ''Deadline'' on August the 2nd, 2011. '''[In progress]'''
     60    * ''Milestone'': Rating integration. ''Deadline'' on August the 2nd, 2011. '''[Executed]'''
    6161
    62     * Alternatively if the work of this week is finished the 5th week... ''Milestone'': Merge project with version aptoide version being developed by Duarte Silveira.
     62    * Alternatively if the work of this week is finished the 5th week... ''Milestone'': Merge project with version aptoide version being developed by Duarte Silveira. '''[Not Done]'''
    6363
    6464'''7th week'''
    6565
    66     * Task: Look and feel design;
     66    * Task: Look and feel design; '''[In progress]'''
    6767
    68     * Task: Research on how to;
     68    * Task: Research on how to; '''[In progress]'''
     69   
     70    * Task: Make comments and likes switch when one particular version is selected in the spinner item: '''[In progress]'''
    6971
    70     * ''Milestone'': look and feel implementation. ''Deadline'' on September the 9th, 2011.
    71 
    72 '''8th week'''
    73 
    74     * Task: Tunning and improvements on the enhancements made so far;
    75 
    76     * ''Milestone'': Production of the Javadoc. ''Deadline'' on September the 16th, 2011.
     72    * ''Milestone'': look and feel implementation. ''Deadline'' on September the 9th, 2011. '''[In progress]'''
    7773
    7874== Risk Mitigation, Monitoring and Management Plan ==